The Florida Supreme Court is upholding a lower court ruling that ordered a massive nuclear plant expansion to be redone to meet environmental and other concerns.
Justices in a brief-one page order on Friday rejected an appeal filed by Florida Power & Light.
Last year, the 3rd District Court of Appeal in Miami reversed a 2014 decision by Gov. Rick Scott and the Cabinet to approve construction of two nuclear reactors by FPL at its Turkey Point plant near Homestead. The project, costing up to $18 billion, would add about 2,200 megawatts of electric power or enough to supply 750,000 homes.
A three-judge panel ruled the governor and Cabinet failed to account for environmental regulations meant to protect the Everglades and endangered birds that make their home in the wetlands.